County Building #1 https://www.thebatavian.com/ en https://www.thebatavian.com/themes/barrio_batavian/images/thebatavian_logo.png County Building #1 https://www.thebatavian.com/ Local Matters © 2008-2023 The Batavian. All Rights Reserved. Tue, 07 May 2024 15:53:55 -0400 https://www.thebatavian.com/themes/barrio_batavian/images/thebatavian_logo.png Wed, 01 May 2024 15:00:00 -0400 Construction is to begin at County Building #1 and Old County Courthouse in Batavia https://www.thebatavian.com/press-release/construction-is-to-begin-at-county-building-1-and-old-county-courthouse-in-batavia
staging-plan-5_1.jpg

Press Release:

Genesee County is upgrading essential infrastructure at County Building No. 1 and the Old County Courthouse to address water penetration concerns and ensure the safety of all occupants and visitors.

Project Details:

  • May 3 - Protective enclosures will be installed around entrances to County Building No. 1 to ensure safety during roof and exterior masonry work.
  • May 6 - Masonry work will commence on the parapet walls, followed by the roof recovery of County Building No. 1 and copper installation at the east entrance of the Old County Courthouse.
  • During the project, all entrances will remain accessible.
  • A protective enclosure for material storage will temporarily block off the central sidewalk, but access will still be available on both the east and west sides of the courtyard.
  • The projects are expected to be completed by the end of June with a 2-week additional window for inclement weather.

Although minimal disruption to daily operations is expected, a safe working zone is of top priority, and the following safety measures have been implemented: 

  • Designated areas for materials and equipment storage.
  • Parking adjustments, including dumpsters in a street parking zone and coned-off contractor access to the lawn.
  • Protective enclosures around entrances to County Building No. 1
  • Please see the included staging plan for more details.

We appreciate the cooperation and understanding of all during this construction period.

]]>
https://www.thebatavian.com/press-release/construction-is-to-begin-at-county-building-1-and-old-county-courthouse-in-batavia#comments https://www.thebatavian.com/press-release/construction-is-to-begin-at-county-building-1-and-old-county-courthouse-in-batavia May 1, 2024, 3:00pm County Building #1 Construction is to begin at County Building #1 and Old County Courthouse in Batavia Press Release <div> <div class="field field--name-field-media-image field--type-image field--label-hidden field__item"> <img loading="lazy" src="https://www.thebatavian.com/sites/default/files/styles/large/public/2024-05/staging-plan-5_1.jpg?itok=aHRiySpo" width="800" height="572" alt="staging-plan-5_1.jpg" class="image-style-large"> </div> </div> <p>Press Release:</p><blockquote><p>Genesee County is upgrading essential infrastructure at County Building No. 1 and the Old County Courthouse to address water penetration concerns and ensure the safety of all occupants and visitors.</p><p>Project Details:</p><ul><li>May 3 - Protective enclosures will be installed around entrances to County Building No. 1</li></ul></blockquote>
Photo: New sign outside County Building #1 https://www.thebatavian.com/howard-owens/photo-new-sign-outside-county-building-1/37489

When I showed up at the park between County Building #1 and the Old Courthouse, I spotted a new directional sign near the main county administration building.

]]>
https://www.thebatavian.com/howard-owens/photo-new-sign-outside-county-building-1/37489#comments https://www.thebatavian.com/howard-owens/photo-new-sign-outside-county-building-1/37489 May 15, 2013, 9:45pm County Building #1 Photo: New sign outside County Building #1 Howard Owens <p></p> <p>When I showed up at the park between County Building #1 and the Old Courthouse, I spotted a new directional sign near the main county administration building.</p>
Photo: Roof replacement work on County Building #1 https://www.thebatavian.com/howard-owens/photo-roof-replacement-work-county-building-1/28876

Workers continue to make progress on the roof replacement of County Building #1 at Court and Ellicott streets.  The $214,000 project was awarded to Elmer W. Davis, Inc., of Rochester.

]]>
https://www.thebatavian.com/howard-owens/photo-roof-replacement-work-county-building-1/28876#comments https://www.thebatavian.com/howard-owens/photo-roof-replacement-work-county-building-1/28876 Oct 28, 2011, 1:55pm County Building #1 Photo: Roof replacement work on County Building #1 Howard Owens <p> </p> <p> Workers continue to make progress on the roof replacement of County Building #1 at Court and Ellicott streets. &nbsp;The $214,000 project was <a href="http://thebatavian.com/howard-owens/lowest-bid-still-over-budget-new-roof-county-building-1/27435">awarded to&nbsp;Elmer W. Davis, Inc.</a>, of Rochester.</p>
Lowest bid still over budget for new roof on County Building #1 https://www.thebatavian.com/howard-owens/lowest-bid-still-over-budget-new-roof-county-building-1/27435 The lowest bid for a new roof on County Building #1 was higher than anticipated and the Genesee County Legislature is being asked to increase the budget allotment for the project.

Assistant County Manager Frank Ciaccia said the lowest bid came in $2,500 more than budgeted, and the original budget contained wiggle room for unanticipated expenses.

Ciaccia asked the Ways and Means Committee today to transfer $12,000 from the county's sales tax reserve to cover the more than $214,000 cost of the roof replacement plus any unforeseen expenses.

"We don't know what we'll find when we take the roof off," Ciaccia said. "We may find some additional damage." 

County Building #1 is the main administration building at 14 W. Main St., Batavia. The original section was built in 1926, with additions being made in 1951 and in the 1990s.

The roof hasn't been replaced since 1985.

The new roof will be a rubber material.

The lowest of four bids came from Elmer W. Davis, Inc., of Rochester.

The committee approved both the budget adjustment and awarding the bid to Davis. The resolutions will be considered by the full legislature at its next meeting.

]]>
https://www.thebatavian.com/howard-owens/lowest-bid-still-over-budget-new-roof-county-building-1/27435#comments https://www.thebatavian.com/howard-owens/lowest-bid-still-over-budget-new-roof-county-building-1/27435 Aug 3, 2011, 10:50pm County Building #1 Lowest bid still over budget for new roof on County Building #1 Howard Owens <p> The lowest bid for a new roof on County Building #1 was higher than anticipated and the Genesee County Legislature is being asked to increase the budget allotment for the project.</p> <p> Assistant County Manager Frank Ciaccia said the lowest bid came in $2,500 more than budgeted, and the original budget</p>