WNY STAMP https://www.thebatavian.com/ en https://www.thebatavian.com/themes/barrio_batavian/images/thebatavian_logo.png WNY STAMP https://www.thebatavian.com/ Local Matters © 2008-2023 The Batavian. All Rights Reserved. Sat, 04 May 2024 21:14:31 -0400 https://www.thebatavian.com/themes/barrio_batavian/images/thebatavian_logo.png Sun, 28 Apr 2024 18:49:00 -0400 Hochul and Schumer announce the start of construction for Edwards Vacuum supply chain facility https://www.thebatavian.com/press-release/hochul-and-schumer-announce-the-start-of-construction-for-edwards-vacuum-supply-chain Press Release:

Governor Kathy Hochul and U.S. Senate Majority Leader Charles Schumer today announced the start of construction on the first phase of the $319 million Edwards Vacuum dry pump manufacturing facility, located in the Genesee County town of Alabama. 

The British-based global leader in vacuum and abatement equipment for the semiconductor industry, part of the Atlas Copco Group, chose the Western New York Science & Technology Advanced Manufacturing Park in Genesee County as the location for its new U.S. dry pump manufacturing facility. 

The technology produced at the new facility is a vital component to controlling the highly sensitive environment of semiconductor manufacturing processes. Edwards Vacuum's decision to invest in New York State followed the passage of the federal CHIPS and Science Act, New York’s Green CHIPS legislation, and the domestic semiconductor industry growth the complementary programs have spurred, including Micron's unprecedented $100 billion commitment to Central New York, which is expected to create nearly 50,000 jobs.

“As a Western New York native, I experienced the years of decline from the exodus of manufacturing from Upstate New York,” Governor Hochul said. “Those days are over. The start of construction on the newest Edwards Vacuum facility signals the beginning of a new chapter for both Western New York and the Finger Lakes regions.  Edwards’ choice to build in New York State brings hundreds of good paying jobs and millions of dollars in investment Upstate while helping strengthen our domestic semiconductor supply chain, shorten delivery times for suppliers like Micron, reduce carbon emissions, and bolster national security.”

Senate Majority Leader Chuck Schumer said, “Today is a great day for the Western New York and Finger Lakes region, with Edwards Vacuum breaking ground on its $300+ million manufacturing plant, which will create an estimated 600 good-paying jobs and boost New York’s already booming semiconductor supply chain. Thanks to my CHIPS & Science Act, which continues to deliver investment after investment for Upstate NY, we are adding another stop to our semiconductor superhighway along the booming I-90 corridor Tech Hub with Edwards Vacuum’s groundbreaking today. I pushed Edwards Vacuum to come to New York because I knew we had the resources, infrastructure, and most importantly, the world-class workforce, to host this major company right here in Genesee County. Edwards is a leading developer of some of the most cutting-edge dry pumps needed to bring the massive cleanrooms of chip manufacturing fabs to life, and with their investment, we are helping bring one of the most critical elements of the semiconductor supply chain to Upstate NY. This is yet another example of my CHIPS & Science Law bringing manufacturing back to America, especially Upstate NY, and is only the beginning of the next chapter in Upstate NY’s manufacturing renaissance.”

Construction on the $127 million first phase of Edwards Vacuum's 240,000 square-foot campus will include manufacturing, warehouse, and administration facilities, with a capacity to produce 10,000 dry pumps per year. The all-electric facility will strive for LEED certification, with a majority of the power generated via hydroelectricity.

Edwards’ commitment to build in the U.S. comes after significant investments by the Biden Administration to increase domestic chip manufacturing, and the passage of the federal CHIPS and Science Act and New York’s Green CHIPS legislation, as well as a growing need to support its customers in North America. Edwards dry pumps are currently manufactured in Asia. By bringing manufacturing to New York, Edwards customers – including Micron and GlobalFoundries in New York, and Intel in Ohio – will experience shorter wait times, improved responsiveness and reduced CO2 emissions from an American-made product. Edwards estimates that when phase one is operational, it will reduce CO2 emissions by 13,000 tons per year.

Empire State Development has awarded Edwards Vacuum up to $21 million through a combination of performance-based Excelsior Jobs Tax Credits and Investment Tax Credits in exchange for 600 jobs, and an additional $1 million to support workforce development efforts and the training of a diverse and inclusive workforce. Additionally, the New York Power Authority is supporting the project though a 4.9-megawatt (MW) low-cost Niagara hydropower allocation and a 2.1 MW of High Load Factor power allocation that NYPA will procure for Edwards on the energy market. Low-cost Niagara hydropower is available for companies within a 30-mile radius of the Power Authority's Niagara Power Project or businesses in Chautauqua County.

Empire State Development President, CEO and Commissioner Hope Knight said, “The start of construction for Edwards Vacuum’s new facility signals that hundreds of good jobs and millions of dollars in investments are headed to Upstate New York. We are well on our way to becoming a global hub for advanced manufacturing and building a strong semiconductor ecosystem in New York State.”

New York Power Authority President and CEO Justin E. Driscoll said, “By leveraging low-cost hydropower, NYPA plays a pivotal role in attracting manufacturers of advanced technologies to New York. Edwards will be a key supply chain partner in New York’s globally recognized semiconductor industry, and the firm’s expansion will stimulate the region’s economy—creating hundreds of jobs and spurring hundreds of millions in capital investments.”

Semiconductors, and their supply chain partners, are vital to the nation's economic strength, serving as the brains of modern electronics, and enabling technologies critical to U.S. economic growth, national security, and global competitiveness. The industry directly employs over 277,000 people in the U.S. and supports more than 1.8 million additional domestic jobs. Semiconductors are a top five U.S. export, and the industry is the number one contributor to labor productivity, supporting improvements to the effectiveness and efficiency of virtually every economic sector — from farming to manufacturing.

Governor Hochul has taken significant action to ensure that New York plays a vital role in the reshoring of the semiconductor industry including New York's nation-leading Green CHIPS program that is attracting top semiconductor manufacturing businesses to the state and securing commitments to good-paying jobs, sustainability, and community benefits. Additionally, Governor Hochul created the $200 FAST NY program in 2022 to support the preparation and development of sites across the state. This program was designed to jumpstart New York's shovel-readiness and increase its attractiveness to large employers, such as semiconductors and clean tech and high-tech manufacturing companies. Since the program’s inception, ESD has awarded $175 million to 20 sites across every upstate region, including the Science & Technology Advanced Manufacturing Park (STAMP), to develop more than 2,500 acres. Governor Hochul also created the Governor’s Office of Semiconductor Expansion, Management, and Integration (GO-SEMI), which leads statewide efforts to develop the chipmaking sector.

In the FY 2025 Enacted Budget, Governor Hochul doubled down on her commitment to establish New York as a global hub for semiconductor research and manufacturing, including:

$100 million in funding for additional rounds of the FAST NY program.

$500 million for NY CREATES’ Albany Nanotech Complex – with a total State investment of $1 billion – to jumpstart a $10 billion partnership that will bring the future of advanced semiconductor research to New York’s Capital Region by creating the nation’s first and only publicly owned High NA EUV Lithography Center.

$200 million to establish One Network for Regional Advanced Manufacturing Partnerships (ON-RAMP) – a network of four new workforce development centers to prepare New Yorkers for the jobs of the future created by companies like Micron and Edwards Vacuum.

The bipartisan CHIPS and Science Act creates an Investment Tax Credit for semiconductor manufacturing facilities and supply chain partners such as Edwards Vacuum as well as a first-of-its-kind $52 billion in federal incentives, which Edwards is pursuing, to spur American semiconductor research, development, manufacturing, and workforce training to bring good-paying jobs back from overseas, strengthen national security, and reestablish America's technological leadership. The bill requires recipients of these incentives to make significant worker and community investments that support broad-based economic growth.

Accelerating Finger Lakes Forward

Today’s announcement complements “Finger Lakes Forward,” the region’s comprehensive strategy to generate  robust economic growth and community development. The regionally designed plan focuses on investing in key industries including photonics, agriculture‎ and food production, and advanced manufacturing. More information is available here.​

Senator Kirsten Gillibrand said, “I am thrilled to see the start of construction on the Edwards Vacuum facility in Genesee County, which will create hundreds of good-paying jobs and grow the economies of both Western New York and the Finger Lakes. The construction of the Edwards Vacuum facility is just the beginning as New York continues to grow as a global leader in semiconductor manufacturing. I’m proud to have fought to pass the CHIPS and Science Act that helped lay the groundwork for companies like Edwards Vacuum to expand in New York, and I look forward to seeing the growth this facility brings to the region for years to come.”

Representative Joe Morelle said, “This exciting announcement is further proof of our region’s leadership in the global semiconductor industry. Not only will construction of Edwards Vacuum strengthen our supply chain and create good-paying job opportunities, it will also grow our economy and enhance our competitiveness on the world stage. I’m proud to have helped facilitate investments like this by passing the CHIPS and Science Act, and I look forward to continuing our work to cement our position as a center of innovation.”

State Senator George M. Borrello said, “This groundbreaking of Edward’s Vacuum and the investment, jobs and economic growth that will follow it will usher in a new chapter for Genesee County and strengthen its growing status as a hub for tech manufacturing. The path to this landmark moment was fueled by a grand vision for the STAMP site and years of planning, funding and hard work. Driving it forward all along was the conviction that this region and its world class workforce had the ingredients for success. The collaboration of dedicated local, state and federal partners brought us to this historic achievement and reflect our shared commitment to upstate’s resurgence. The future is limitless.”

Assemblymember Steven Hawley said, “I’m proud to see the announcement today that Edward’s Vacuum is starting construction at the STAMP mega-site. The 139th Assembly District has always been a hub of innovation and it's only fitting that it will be at the center of New York’s emerging semiconductor industry. This project is another step in the right direction toward growing the local economy, creating good-paying jobs and making New York a leader in this sector.”

Genesee County Legislature Chair Shelley Stein said, “Today’s announcement is reaffirmation of the positive attributes of Genesee County in bringing a company with the stature of Edwards Vacuum to the STAMP mega-site. Our community can be proud to be part of the growing semiconductor industry not only in New York State but across the nation and world. Genesee County’s location, people, and infrastructure make STAMP the ideal place for future industry growth here. We look forward to Edwards Vacuum’s continued success.”

Town of Alabama Supervisor Rob Crossen said, “We congratulate Edwards Vacuum on the start of construction at the STAMP mega-site. This latest milestone in the development of STAMP continues the realization of our shared vision for investments that improve the economy, attract good paying jobs, and enhance our community.”

GCEDC President and CEO Steve Hyde said, “As we work to grow our economy and deliver family-sustaining careers at the STAMP mega-site, having partners like Edwards Vacuum, Senator Schumer, and Governor Hochul is gratifying. The start of construction for this critical semiconductor industry project demonstrates the impact that STAMP provides in our shared state and federal vision to grow semiconductor and related advanced manufacturing sectors.”

Greater Rochester Enterprise President and CEO Matt Hurlbutt said, “Top-tier talent, world-class R&D resources, access to low-cost hydropower, and the premier infrastructure available at the STAMP mega site are some of the assets that made the Greater Rochester, NY region the right place for Edwards' expansion. We celebrate Edwards' groundbreaking at STAMP and the significant partnership Greater Rochester Enterprise (GRE) has formed with Edwards leaders and our regional economic development partners to reach this milestone in the company's expansion plans. GRE will continue to support Edwards by facilitating connections between the company's leaders and key stakeholders from business, community, and academia. This collaborative effort is aimed at ensuring a successful launch and further enhancing the ties between Edwards, the community, and the region's thriving advanced manufacturing and semiconductor sectors. We look forward to the positive impact this expansion will have on the Greater Rochester, NY region.”

Phase One Renderings Available Here.

]]>
https://www.thebatavian.com/press-release/hochul-and-schumer-announce-the-start-of-construction-for-edwards-vacuum-supply-chain#comments https://www.thebatavian.com/press-release/hochul-and-schumer-announce-the-start-of-construction-for-edwards-vacuum-supply-chain Apr 28, 2024, 6:49pm WNY STAMP Hochul and Schumer announce the start of construction for Edwards Vacuum supply chain facility Press Release <p>Press Release:</p><blockquote><p>Governor Kathy Hochul and U.S. Senate Majority Leader Charles Schumer today announced the start of construction on the first phase of the $319 million Edwards Vacuum dry pump manufacturing facility, located in the Genesee County town of Alabama.&nbsp;</p><p>The British-based global leader in vacuum and abatement equipment for</p></blockquote>
GCEDC announces changes to sewer line plans for WNY STAMP https://www.thebatavian.com/press-release/gcedc-announces-changes-to-sewer-line-plans-for-wny-stamp/639168 Press release:

“The Genesee County Economic Development Center (GCEDC) is pleased to announce that we are working closely with the towns of Oakfield and Alabama, along with the village of Oakfield and regulatory agencies, to construct a force main to accommodate the current projects at STAMP and a potential future project.

“This project would result in capital improvements to the Village of Oakfield wastewater treatment plant, including the installation of equipment to reduce the current phosphorus discharge into Oak Orchard Creek.

“As the Oakfield line cannot fully replace the Orleans County line, we will continue to pursue the force main to Oak Orchard Creek in the town of Shelby through a different construction method, and we look forward to working with the United States Department of Fish and Wildlife and the Tonawanda Seneca Nation as this process moves forward. The Oakfield plan alleviates the timing pressures for the build-out of the force main to Oak Orchard Creek.

“As a result of being recently notified by the USFWS that our permit for horizontal directional drilling for the force main to Oak Orchard Creek in the town of Shelby has been terminated, we are in the process of submitting a new permit application to propose an open cut construction method which will avoid the types of incidents that resulted from the former method.

“The determination by USFWS is unrelated to claims made by Orleans County regarding the force main to Oak Orchard Creek.  Those claims brought by Orleans County were recently dismissed by the State Supreme Court following an Article 78 hearing.”

]]>
https://www.thebatavian.com/press-release/gcedc-announces-changes-to-sewer-line-plans-for-wny-stamp/639168#comments https://www.thebatavian.com/press-release/gcedc-announces-changes-to-sewer-line-plans-for-wny-stamp/639168 Apr 25, 2024, 2:47pm WNY STAMP GCEDC announces changes to sewer line plans for WNY STAMP Press Release <p>Press release:</p><blockquote><p><span>“The Genesee County Economic Development Center (GCEDC) is pleased to announce that we are working closely with the towns of Oakfield and Alabama, along with the village of Oakfield and regulatory agencies, to construct a force main to accommodate the current projects at STAMP and a potential future</span></p></blockquote>
Plug Power awarded $76M from DOE, still awaiting word on loan, reports record revenue but still no profits https://www.thebatavian.com/howard-owens/plug-power-awarded-76m-from-doe-still-awaiting-word-on-loan-reports-record-revenue-but
plug power WNY STAMP
File photo of Plug Power facility under construction at WNY STAMP.
By Howard Owens.

The Department of Energy has awarded grants totaling $75.7 million to Plug Power, the Latham-based green hydrogen power company currently constructing a production facility in WNY STAMP in the town of Alabama.

The funds are part of a $1 trillion infrastructure bill approved by Congress and President Joe Biden in 2021 and are intended to help with research and development of hydrogen fuel production.

The company has also applied for a $1.6 billion low-interest loan from the DOE. That loan is apparently still under consideration.

Plug Power is betting that hydrogen power will become a big winner in the race to develop clean, renewable energy to sustain the economy and protect the environment in the coming decades. The Latham-based company specializes in "green hydrogen," which is the generation of hydrogen fuel using renewable energy sources such as solar and hydropower. An apparent attraction of WNY STAMP is the ability at that location to tap into hydropower generated by Niagara Falls.

Plug Power aims to provide customers with fuel cells, electrolyzers (splitting water into hydrogen and oxygen), to liquid hydrogen fuel. Plug Power wants to provide distribution, delivery, and services and foresees a future for hydrogen that includes uses such as long-haul trucking.

Plug Power's executives have set ambitious goals -- producing 2,000 tons of hydrogen daily by 2030. At that rate, the company hopes to generate $20 billion in annual revenue at that point with a profit margin of at least 30 percent.  

“The Bipartisan Infrastructure & Jobs Law is helping supercharge Upstate NY’s clean hydrogen sector. With this federal funding, Plug Power and other cutting-edge companies will be able to increase production capacity and spark new innovation to reach the next frontier of clean hydrogen manufacturing and research, all while supporting good-paying clean energy jobs and boosting the fight against climate change,” said, Sen. Charles Schumer. “Clean green hydrogen is one of the most exciting forms of new energy production, and with the major federal investments being made thanks to the Bipartisan Infrastructure Law and Inflation Reduction Act I championed, Upstate NY is poised to lead the way in powering America’s clean energy future.”

The grants are divided into two components.

The company will receive $45.7 million for the following project description:

The goal of this project is to establish and implement automation capabilities within our high-performance PEM stack manufacturing facility in Rochester, New York capable of producing 5,000 1 MW stacks per year.

This project will scale up manufacturing of proton exchange membrane electrolyzer stacks to the multi-GW scale, driving down costs to meet DOE targets. This project will automate membrane electrode assembly fabrication and stack assembly and enable automated inspection with machine learning to accelerate factory acceptance testing.

The project description for the second grant, $30 million:

This project will demonstrate a production pathway to meet a projected 2030 system cost of $80/kW for 100,000 heavy-duty fuel cell systems per year and automate the manufacturing of high-performance, low-defect membrane electrode assemblies in collaboration with the National Renewable Energy Lab.

The project will demonstrate an innovative expansion of their current manufacturing line.

“We are very appreciative and excited about the DOE's clean energy manufacturing initiatives and their profound impact on propelling Plug's industry-leading manufacturing capabilities in fuel cell and electrolyzer MEAs (Membrane Electrode Assemblies) and stacks," said Andy Marsh, CEO of Plug. “Congress enacted these policies to advance hydrogen and fuel cells as vital components of the United States’ climate strategy.  This funding will advance Plug’s fuel cell and electrolyzer manufacturing capabilities, create good paying jobs in New York, and fortify the region’s leadership in the national clean energy transition.”

The company selected WNY STAMP for the construction of a liquid hydrogen plant in February 2021.  The plant will cost more than $290 million to complete. 

Plug Power expects to generate 74 tons per day of liquid hydrogen at its WNY STAMP plant. The company recently opened two new production facilities in Georgia and Tennessee, and the WNY STAMP plant is expected to open in early 2025.

Empire State Development is scheduled to pay up to $2 million in Excelsior Tax Credits in exchange for the creation of 68 jobs at the plant, or about $2,941 per job per year over 10 years. Plug Power is not eligible to receive the tax credits until the jobs are filled. The average starting salary is expected to be approximately $70,000 plus benefits.

As part of the project, Plug Power agreed to invest $55 million in a 450-megawatt electrical substation that will make electricity available to other WNY STAMP tenants.

The company received $118.2 million in sales and property tax exemptions from the Genesee County Economic Development Center. Over the 20-year life of the property tax extensions, Plug Power will make payments in lieu of taxes totaling $2.3 million annually, which will be shared by Genesee County, the Town of Alabama, and the Oakfield-Alabama School District.  Each jurisdiction will also receive an increasing amount of property tax payments each year over the life of the agreement.

In accordance with Security and Exchange Commission Rules, Plug Power disclosed in November that a shortage of cash threatened its ability to remain a "going concern" within the following 12 months.  It suggested it could raise more cash by selling stock and that the company expected to receive a sizable loan from the Department of Energy.

Since then, Plug Power authorized B. Riley Securities to offer additional public shares of the company for sale at market rate with the goal of raising an additional $1 billion in capital.  That agreement was announced in January.  Since then, it has reportedly sold 77,417,069 new shares of stock, raising more than $300 million in cash. The company is continuing to sell new shares with a goal of selling another $700 million in 2024.

On Monday morning, the company announced its fourth quarter 2023 results and that it has removed its "going concern" guidance, stating, "The Company has determined it has sufficient cash on hand coupled with available liquidity to fund its ongoing operations for the foreseeable future."

It also announced record revenue of $891 million for the year, a 27% increase over the prior year.

However, the company continues to lose money and has never turned a profit, which, 25 years into its existence, continues to spook investors. After the Q4 report was released on Monday, the price per share of the company's stock dropped 17 cents and closed at $3.37. It hasn't traded above $5 since November. In early 2021, it was trading for more than $60 a share.

For previous Plug Power coverage, click here.

]]>
https://www.thebatavian.com/howard-owens/plug-power-awarded-76m-from-doe-still-awaiting-word-on-loan-reports-record-revenue-but#comments https://www.thebatavian.com/howard-owens/plug-power-awarded-76m-from-doe-still-awaiting-word-on-loan-reports-record-revenue-but Mar 14, 2024, 7:30am WNY STAMP Plug Power awarded $76M from DOE, still awaiting word on loan, reports record revenue but still no profits Howard Owens <p>The Department of Energy has awarded grants totaling $75.7 million to Plug Power, the Latham-based green hydrogen power company currently constructing a production facility in WNY STAMP in the town of Alabama.</p>
Orleans County lawsuit aimed at stopping WNY STAMP pipeline dismissed over 8-year delay in objecting https://www.thebatavian.com/tom-rivers/orleans-county-lawsuit-aimed-at-stopping-wny-stamp-pipeline-dismissed-over-8-year-delay
sewer stamp
A sewer line is shown on Aug. 12 on Route 63 in the Town of Alabama. Genesee County Economic Development Center is trying to install the sewer main along 9.5 miles of Route 63 – from the STAMP site to Oak Orchard Creek. Construction was halted before the sewer line made it to Orleans after a lawsuit was filed.
Photo by Tom Rivers.

A State Supreme Court justice on Thursday dismissed a lawsuit and temporary injunction against the construction of a nearly 10-mile-long sewer main from the STAMP manufacturing site in the town of Alabama along Route 63 to Oak Orchard Creek in the town of Shelby.

Judge Frank Caruso ruled in favor of the Genesee County Economic Development Center. GCEDC argued that Orleans County had 23 chances to state its objection to the sewer main since 2016 but waited until construction started to voice its opposition.

Judge Caruso cited the legal argument of “laches,” where there is a lack of diligence in making a legal claim. Attorneys for GCEDC argued in court that waiting until construction commenced on the project should be considered an unreasonable delay.

The judge also ruled in favor of GCEDC due to a statute of limitations. He made his decision from the bench in court today, following about an hour of arguments in the main courtroom of the county courthouse. He will also issue a written decision.

Orleans County officials say the county will appeal the decision and has other court options to try to halt the project.

“The fight here is not over,” said Alex Eaton, an attorney for the Orleans County Legislature. “We have several more paths to prevent Orleans County from becoming a dumping ground for STAMP sewer discharges.”

The county also has a lawsuit to be heard in April about GCEDC using eminent domain to take easements in Orleans County. The attorneys for Orleans said another county’s IDA can’t do eminent domain in another county.

Orleans also supports the Tonawanda Seneca Nation in its litigation against several federal entities regarding the permitting of the sewer pipeline.

“Orleans County leadership remains steadfast in our opposition to anything that puts Oak Orchard Creek in jeopardy,” Eaton, an attorney with Lippes Mathias, said in a statement released from the County Legislature. “The county and its residents rely on the creek for water, recreation and tourism, and that is why we will continue to protect the interests of our community.   Again, while we are disappointed in today’s result, there is a long way to go before this issue is settled.”

Orleans County filed its lawsuit on Sept. 11, naming GCEDC, G. DeVincentis & Son Construction Co., Inc., Genesee Gateway Local Development Corporation, and STAMP Sewer Works, Inc.

Matthew J. Fitzgerald and James O’Connor of Phillips Lytle LLP appeared in court today on behalf of GCEDC. They contended that the sewer main underwent a rigorous environmental review of 9,200-plus pages and was ultimately approved by the state Department of Environmental Conservation, Army Corps of Engineers, and U.S. Fish and Wildlife Service. The attorneys said those agencies found no evidence of harm to Oak Orchard Creek or the community.

The sewer main would allow businesses at the 1,250-acre STAMP to discharge treated sewer water into the Oak Orchard. At STAMP’s peak, the sewer main could discharge up to 6 million gallons daily in the Oak Orchard. The sewer main is imperative for economic development at the site.

“STAMP does not survive without somewhere to discharge the treated sanitary water,” Fitzgerald said in court today.

Fitzgerald said the four-month statute of limitations passed after Orleans filed the Article 78 proceeding on Sept. 11, and the county failed to notify other parties that would be hurt if the lawsuit successfully halted the sewer main.

He said property owners who paid for easements for the temporary construction could lose out on payments. The Town of Alabama would miss out on 100,000 gallons of sewer capacity, and Niagara County Water District would miss out on selling water to the STAMP site. Orleans didn’t factor in those impacts in the lawsuit, Fitzgerald said.

The crux of the case, he said, was the contention that Orleans never gave its support for economic development from another county. But he said Orleans officials were notified in 2016, 2020, 2021, 2022, and 2023 to voice any concerns over STAMP, and GCEDC served as the lead agency.

“The response was silence,” Fitzgerald said. “They slept on their rights for approximately eight years. They could have objected.”

He said STAMP has about $100 million in public funds committed to developing the site so far, and about $1 billion has already been spent or committed in private investment.

Orleans' attorneys contend that Genesee County used its money through its industrial development agency to fund the sewer main and pursue eminent domain in another county, powers that an IDA does not have.

Jennifer Persico, an attorney with Lippes Mathias representing Orleans, said the STAMP sewer project clearly used Genesee County funds to move the project into Orleans County.

The GCEDC attorneys said the project was funded through state grants and wasn’t actually GCEDC money.

The town of Shelby also joined Orleans in the lawsuit. The Shelby attorney, Jeffrey Allen, said Shelby supports the efforts of Orleans County to halt the pipeline before it gets into Orleans. He said there are many violations of general municipal law related to the project.

Shelby previously supported the project, but he said that was a statement considering its environmental impacts.

“The consent was not that they could run roughshod over the autonomy of Orleans County,” Allen said in court.

Eaton, an attorney for Orleans County, said the case could be a landmark for the state. He said the courts should protect smaller neighboring counties from being forced to take on negative impacts from another county’s economic development efforts.

“This would be one of the biggest expansions of IDA power in New York State,” Eaton said.

Tom Rivers is editor OrleansHub.com.

]]>
https://www.thebatavian.com/tom-rivers/orleans-county-lawsuit-aimed-at-stopping-wny-stamp-pipeline-dismissed-over-8-year-delay#comments https://www.thebatavian.com/tom-rivers/orleans-county-lawsuit-aimed-at-stopping-wny-stamp-pipeline-dismissed-over-8-year-delay Mar 7, 2024, 5:15pm WNY STAMP Orleans County lawsuit aimed at stopping WNY STAMP pipeline dismissed over 8-year delay in objecting Tom Rivers <figure role="group" class="caption caption-div"> <div> <div class="field field--name-field-media-image field--type-image field--label-hidden field__item"> <img alt="sewer stamp" class="image-style-large" height="353" loading="lazy" src="https://www.thebatavian.com/sites/default/files/styles/large/public/2024-03/081223_stamp1.jpg?itok=UUr1aqCD" width="700"> </div> </div> <figcaption><em>A sewer line is shown on Aug. 12 on Route 63 in the Town of Alabama. Genesee County Economic Development Center is trying to install the sewer main along 9.5 miles of Route 63 – from the STAMP site to Oak Orchard Creek. Construction was halted before the sewer line made it to Orleans after a lawsuit was filed.</em><br><em>Photo by Tom Rivers.</em></figcaption> </figure> <p>A State Supreme Court justice on Thursday dismissed a lawsuit and temporary injunction against the construction of a nearly 10-mile-long sewer main from the STAMP manufacturing site in the town of Alabama along Route 63 to Oak Orchard Creek in the town of Shelby.</p><p>Judge Frank Caruso ruled in</p>
Facing challenges and skeptics, Plug Power officials say new plant expected to begin production in 2025 https://www.thebatavian.com/howard-owens/facing-challenges-and-skeptics-plug-power-officials-say-new-plant-expected-to-begin
plug power WNY STAMP
Plug Power in WNY STAMP.
Photo by Howard Owens.

The company's share price hasn't risen above $5 in four months after executives informed investors that it is facing a cash flow problem, and while it has made progress on improving its cash holdings and has increased production at plants in Tennessee and Georgia, there are stock analysts downgrading Plug Power as an investment opportunity. 

Even so, Plug Power's leadership indicates the company is plowing ahead with plans to build the nation's leading fully integrated hydrogen power supply company -- a revolution in alternative energy production if Plug Power can pull it off.

]]>
https://www.thebatavian.com/howard-owens/facing-challenges-and-skeptics-plug-power-officials-say-new-plant-expected-to-begin#comments https://www.thebatavian.com/howard-owens/facing-challenges-and-skeptics-plug-power-officials-say-new-plant-expected-to-begin Feb 9, 2024, 8:00am WNY STAMP Facing challenges and skeptics, Plug Power officials say new plant expected to begin production in 2025 Howard Owens <figure role="group" class="caption caption-div"> <div> <div class="field field--name-field-media-image field--type-image field--label-hidden field__item"> <img alt="plug power WNY STAMP" class="image-style-large" height="502" loading="lazy" src="https://www.thebatavian.com/sites/default/files/styles/large/public/2024-02/plug-power-feb-2024-b.jpg?itok=vaQ6oQY-" width="800"> </div> </div> <figcaption><em>Plug Power in WNY STAMP.</em><br><em>Photo by Howard Owens.</em></figcaption> </figure> <p>The company's share price hasn't risen above $5 in four months after executives informed investors that it is facing a cash flow problem, and while it has made progress on improving its cash holdings and has increased production at plants in Tennessee and Georgia, there are stock analysts downgrading Plug Power as an investment opportunity.&nbsp;</p><p>Even so, Plug Power's leadership indicates the company is plowing ahead with plans to build the nation's leading fully integrated hydrogen power supply company -- a revolution in alternative energy production if Plug Power can pull it off.</p>
Seneca Nation sues Wildlife Service over approval of STAMP pipeline https://www.thebatavian.com/howard-owens/seneca-nation-sues-wildlife-service-over-approval-of-stamp-pipeline/637470 Asserting rights over the Iroquois National Wildlife Refuge, the Tonawanda Seneca Nation has filed a lawsuit against the federal government in U.S. District Court over the U.S. Fish and Wildlife Service’s approval of a right of way for an industrial wastewater pipeline through the Iroquois National Wildlife Refuge.

The lawsuit asserts that the Nation has standing to sue because the refuge is historically and culturally interrelated with the Nation's ancestral territory, even though it is outside the boundaries of the Tonawanda Indian Reservation. 

]]>
https://www.thebatavian.com/howard-owens/seneca-nation-sues-wildlife-service-over-approval-of-stamp-pipeline/637470#comments https://www.thebatavian.com/howard-owens/seneca-nation-sues-wildlife-service-over-approval-of-stamp-pipeline/637470 Dec 5, 2023, 5:34pm WNY STAMP Seneca Nation sues Wildlife Service over approval of STAMP pipeline Howard Owens <p>Asserting rights over the Iroquois National Wildlife Refuge, the Tonawanda Seneca Nation has filed a lawsuit against the federal government in U.S. District Court over the U.S. Fish and Wildlife Service’s approval of a right of way for an industrial wastewater pipeline through the Iroquois National Wildlife Refuge.</p><p>The lawsuit asserts that the Nation has standing to sue because the refuge is historically and culturally interrelated with the Nation's ancestral territory, even though it is outside the boundaries of the Tonawanda Indian Reservation.&nbsp;</p>
Plug Power's financial filing raises concerns about stability of company https://www.thebatavian.com/howard-owens/plug-powers-financial-filing-raises-concerns-about-stability-of-company/637189
Photo via Genesee County Economic Development Center.
Photo via Genesee County Economic Development Center.

Uncertain about its ability to raise more investment capital, Plug Power, currently building a hydrogen fuel cell plant in WNY STAMP informed the Security and Exchange Commission in a filing on Friday that it may not have the ability to remain a "going concern" over the next 12 months

]]>
https://www.thebatavian.com/howard-owens/plug-powers-financial-filing-raises-concerns-about-stability-of-company/637189#comments https://www.thebatavian.com/howard-owens/plug-powers-financial-filing-raises-concerns-about-stability-of-company/637189 Nov 11, 2023, 11:00am WNY STAMP Plug Power's financial filing raises concerns about stability of company Howard Owens <figure role="group" class="caption caption-div"> <div> <div class="field field--name-field-media-image field--type-image field--label-hidden field__item"> <img alt="Photo via Genesee County Economic Development Center." class="image-style-large" height="453" loading="lazy" src="https://www.thebatavian.com/sites/default/files/styles/large/public/2023-11/6470f12d016fa.image__0.jpg?itok=qv31CpGb" width="800"> </div> </div> <figcaption><em>Photo via Genesee County Economic Development Center.</em></figcaption> </figure> <p>Uncertain about its ability to raise more investment capital, Plug Power, currently building a hydrogen fuel cell plant in WNY STAMP informed the <a href="https://d18rn0p25nwr6d.cloudfront.net/CIK-0001093691/f2d39c6a-e710-49a7-923e-4634d2de39f1.pdf">Security and Exchange Commission in a filing on Friday</a> that it may not have the ability to remain a "going concern" over the next 12 months</p>
Undeterred by legal challenges, Hyde bullish on STAMP's future https://www.thebatavian.com/howard-owens/undeterred-by-legal-challenges-hyde-bullish-on-stamps-future/637117
WNY STAMP map

It's been 15 years since Steve Hyde first conceived of a massive, high-tech industrial park in Genesee County, and in 2023 Hyde is still focused on turning WNY STAMP into a fully realized mega site in the Town of Alabama even as the project faces its biggest legal challenges yet.

Hyde, the CEO of the Genesee County Economic Development Center, and Jim Krencik, the agency's marketing director, spoke with The Batavian on Friday primarily to discuss a new $56 million round of funding from New York State.

The infusion of cash, Hyde shared in his unbowed enthusiasm for all things STAMP, will help take STAMP -- with two projects already being developed -- to the next level, making it more attractive to a new wave of site selectors.

]]>
https://www.thebatavian.com/howard-owens/undeterred-by-legal-challenges-hyde-bullish-on-stamps-future/637117#comments https://www.thebatavian.com/howard-owens/undeterred-by-legal-challenges-hyde-bullish-on-stamps-future/637117 Nov 6, 2023, 8:00am WNY STAMP Undeterred by legal challenges, Hyde bullish on STAMP's future Howard Owens <div> <div class="field field--name-field-media-image field--type-image field--label-hidden field__item"> <img loading="lazy" src="https://www.thebatavian.com/sites/default/files/styles/large/public/2023-11/stamp.simplemap.extra_.jpg?itok=hcb4OqNE" width="800" height="605" alt="WNY STAMP map" class="image-style-large"> </div> </div> <p>It's been 15 years since Steve Hyde first conceived of a massive, high-tech industrial park in Genesee County, and in 2023 Hyde is still focused on turning WNY STAMP into a fully realized mega site in the Town of Alabama even as the project faces its biggest legal challenges yet.</p><p>Hyde, the CEO of the Genesee County Economic Development Center, and Jim Krencik, the agency's marketing director, spoke with The Batavian on Friday primarily to discuss <a href="https://www.thebatavian.com/press-release/hochul-announces-56-million-funding-for-stamp-as-part-of-larger-business-development">a new $56 million round of funding from New York State</a>.</p><p>The infusion of cash, Hyde shared in his unbowed enthusiasm for all things STAMP, will help take STAMP -- with two projects already being developed -- to the next level, making it more attractive to a new wave of site selectors.</p>
Hochul announces $56 million funding for STAMP as part of larger business development program https://www.thebatavian.com/press-release/hochul-announces-56-million-funding-for-stamp-as-part-of-larger-business-development Press release:

Governor Kathy Hochul today announced that nearly $90 million has been awarded for six locations under the Focused Attraction of Shovel-Ready Tracts New York grant program. First announced in February 2022, the program is designed to prepare and develop sites across the state to jumpstart New York’s shovel-readiness and increase its attractiveness to large employers and high-tech manufacturing companies. The program, administered by Empire State Development, will help diversify New York State’s economy while propelling new investments for businesses, communities, and job creation.

“Through the FAST NY grant program, New York is continuing its commitment to investing in and expanding economic growth and opportunity across the state,” Governor Hochul said. “This funding will prepare shovel-ready sites that key industries like semiconductors and renewable energy are looking for and will create good jobs and grow local economies for generations to come.”

There are seven projects mentioned in the press release. Here is the section on WNY STAMP:

  • Genesee County Industrial Development Agency (IDA), Genesee County – $56 million: The Western New York Science Technology Advanced Manufacturing Park (STAMP) is a 1250-acre mega site, with access to significant power, water and completed pre-development. STAMP is the largest remaining site in New York State, which has already committed over $50 million to the site and where Plug Power’s green hydrogen project is currently under construction and Edwards Vacuum will be starting construction on their dry pump factory next spring. STAMP is integral to the recent EDA Regional Tech Hub designation for the Buffalo-Rochester-Syracuse corridor and the state’s strategic goal of creating a “semiconductor superhighway” across Upstate. This phase of the project focuses on building the remaining infrastructure to support advanced manufacturing projects including a wastewater treatment facility and pump station, force-main components, natural gas transmission main tap and extension within the site, road construction improvements and a water transmission main. Total project cost: $62.37 million

Click here to read the full press release.

UPDATE: Statement from GCEDC:

“The FAST NY award announced by Governor Hochul today demonstrates her steadfast commitment to next-generation site development that will bring emerging business sectors in semiconductor and advanced manufacturing to our region.

“This award creates significant momentum in our efforts to design, engineer, and secure permits for infrastructure at STAMP, including current projects that have been announced to date that are anticipated to generate $1 billion of private sector investment and the creation of over 600 family-sustaining jobs.

“The FAST NY award also follows Senate Majority Leader Schumer’s recent announcement of the Buffalo-Rochester-Syracuse regions being designated as a federal Tech Hub, which will only enhance continued interest at STAMP by companies in these business sectors.”

 

]]>
https://www.thebatavian.com/press-release/hochul-announces-56-million-funding-for-stamp-as-part-of-larger-business-development#comments https://www.thebatavian.com/press-release/hochul-announces-56-million-funding-for-stamp-as-part-of-larger-business-development Nov 2, 2023, 3:08pm WNY STAMP Hochul announces $56 million funding for STAMP as part of larger business development program Press Release <p>Press release:</p><blockquote><p>Governor Kathy Hochul today announced that nearly $90 million has been awarded for six locations under the Focused Attraction of Shovel-Ready Tracts New York grant program. <a href="https://www.governor.ny.gov/news/governor-hochul-announces-fast-ny-grant-program-attract-key-industries-shovel-ready-sites">First announced</a> in February 2022, the program is designed to prepare and develop sites across the state to jumpstart New York’s shovel-readiness</p></blockquote>
Complaints raised at planning board meeting about STAMP, Edwards Vacuum, addressed by officials https://www.thebatavian.com/howard-owens/complaints-raised-at-planning-board-meeting-about-stamp-edwards-vacuum-addressed-by
Kirk Scirto, Akron
Dr. Kirk Scirto, a family physician in Akron, spoke in opposition on Thursday night to plans for Edwards Vacuum and WNY STAMP.
Photo by Howard Owens.

CLARIFICATION: Dr. Kirk Scirto informed us on Oct. 18 that he did not say that he represented the Seneca Nation. 

It's unusual for opponents of a development project to speak at Genesee County Planning Board meetings, but two people opposed the proposed Edwards Vaccum plant at WNY STAMP and

]]>
https://www.thebatavian.com/howard-owens/complaints-raised-at-planning-board-meeting-about-stamp-edwards-vacuum-addressed-by#comments https://www.thebatavian.com/howard-owens/complaints-raised-at-planning-board-meeting-about-stamp-edwards-vacuum-addressed-by Oct 13, 2023, 7:17pm WNY STAMP Complaints raised at planning board meeting about STAMP, Edwards Vacuum, addressed by officials Howard Owens <figure role="group" class="caption caption-div"> <div> <div class="field field--name-field-media-image field--type-image field--label-hidden field__item"> <img alt="Kirk Scirto, Akron" class="image-style-large" height="532" loading="lazy" src="https://www.thebatavian.com/sites/default/files/styles/large/public/2023-10/edwards-vacuum-county-planning-board-2023-2.jpg?itok=vP-cattT" width="800"> </div> </div> <figcaption><em>Dr. Kirk Scirto, a family physician in Akron, spoke in opposition on Thursday night to plans for Edwards Vacuum and WNY STAMP.</em><br><em>Photo by Howard Owens.</em></figcaption> </figure> <p><em>CLARIFICATION: Dr. Kirk Scirto informed us on Oct. 18 that he did not say that he represented the Seneca Nation.&nbsp;</em></p><p>It's unusual for opponents of a development project to speak at Genesee County Planning Board meetings, but two people opposed the proposed Edwards Vaccum plant at WNY STAMP and</p>