Gallina Development https://www.thebatavian.com/ en https://www.thebatavian.com/themes/barrio_batavian/images/thebatavian_logo.png Gallina Development https://www.thebatavian.com/ Local Matters © 2008-2023 The Batavian. All Rights Reserved. Wed, 24 Apr 2024 16:44:41 -0400 https://www.thebatavian.com/themes/barrio_batavian/images/thebatavian_logo.png Wed, 20 Apr 2022 10:30:00 -0400 Town planners approve additions at O-At-Ka Milk, Gateway GS LL site on Call Parkway https://www.thebatavian.com/mike-pettinella/town-planners-approve-additions-at-o-at-ka-milk-gateway-gs-ll-site-on-call-parkway The Town of Batavia Planning Board on Tuesday night approved site plans for additions at O-At-Ka Milk Products on Ellicott Street Road and to buildings under construction by Gallina Development of Rochester at the Gateway GS LLC site on Call Parkway, north of the Thruway interchange.

Kelly Finch, senior director of engineering and operational technology at O-At-Ka Milk, explained that the project involves “increasing the plant’s capacity by fully utilizing what is there.”

Specifically, O-At-Ka Milk plans to construct a 58- by 70-square-foot addition that includes three storage tanks for the company’s growing alcohol-based beverage operation.

Finch said one of the tanks measures 15 feet high by 8 feet in diameter and the other two measure 28 feet high by 12.5 feet in diameter. The addition is to be placed on the south side of the property, which spans the corner of Ellicott Street Road and Cedar Street.

Rod Ives, civil engineer for Napierala Consulting of Syracuse, shared that the addition will go in an area that currently is paved, resulting in no stormwater runoff.

The planning board conducted a State Environmental Quality Review and found no adverse effects before voting in favor of the site plan.

Following that, the board voted favorably on the SEQR and site plan submitted by Gallina Development to change the square footage of two office buildings under construction.

The first would increase from 22,000 square feet to 30,000 square feet and the second would go from 27,000 square feet to 33,600 square feet. A third building, designated for future construction, will be reduced from 27,000 square feet to 17,400 square feet.

Overall, the total area of development originally approved – five building lots -- would remain at 135,000 square feet.

]]>
https://www.thebatavian.com/mike-pettinella/town-planners-approve-additions-at-o-at-ka-milk-gateway-gs-ll-site-on-call-parkway#comments https://www.thebatavian.com/mike-pettinella/town-planners-approve-additions-at-o-at-ka-milk-gateway-gs-ll-site-on-call-parkway Apr 20, 2022, 10:30am Gallina Development Town planners approve additions at O-At-Ka Milk, Gateway GS LL site on Call Parkway mikepett <p>The Town of Batavia Planning Board on Tuesday night approved site plans for additions at O-At-Ka Milk Products on Ellicott Street Road and to buildings under construction by Gallina Development of Rochester at the Gateway GS LLC site on Call Parkway, north of the Thruway interchange.</p> <p>Kelly Finch, senior director</p>
GCEDC Board accepts applications for incentives for warehouse, DRI project, and two solar projects https://www.thebatavian.com/press-release/gcedc-board-accepts-applications-for-incentives-for-warehouse-dri-project-and-two Press release:

The Genesee County Economic Development Center (GCEDC) Board of Directors approved an initial application for incentives and final incentives for projects proposing to invest $18.5 million at its July 1 board meeting.

Gateway GS LLC (Gallina Development) plans to build the third phase of its flex campus at the GCEDC’s Gateway II Corporate Park in the Town of Batavia. The $2.36 million investment will create a 27,000-square-foot facility that would be completed in 2022 for a single logistics-distribution tenant. The future tenant is estimated to create 21 new jobs at an average annual salary of $42,000. 

“This investment and the interest generated for the high-quality facilities Gallina Development is constructing at the Gateway II Corporate Park continue the success of Genesee County’s shovel-ready business park development strategy,” said Steve Hyde, president and CEO of the GCEDC.

The GCEDC Board of Directors accepted an initial application for the project. Gallina Development is seeking approximately $386,891 in sales, mortgage, and property tax incentives. The project is estimated to generate $28 in economic activity for every $1 of public investment.

The GCEDC Board of Directors also approved a final resolution for Just Chez Realty LLC. After making improvements to the first floor of 206 E. Main St. in the City of Batavia, Chez Realty LLC is proposing to invest $450,000 to construct two market-rate apartments on the second floor.

The redevelopment of the 13,324-square-foot building is part of the City of Batavia’s Downtown Revitalization Initiative (DRI). Just Chez Realty will receive approximately $21,000 in sales tax exemptions.

The GCEDC Board of Directors also accepted an application for two community solar projects on Ellicott Street Road in the Town of Batavia. Trousdale Solar LLC and Trousdale Solar II LLC are proposing projects that would generate 5 MW and 4 MW of electricity.

The PILOTs (Payment In Lieu Of Taxes) would result in payments of approximately $930,000 to the Batavia City School District and Genesee County over 15 years. The proposed project agreement is estimated to provide $2.5 million in property and sales tax incentives between the two projects.

With the acceptance of the applications from Gateway GS and Trousdale Solar LLC and Trousdale Solar II LLC, public hearings on the proposed projects will be scheduled in the coming weeks.

]]>
https://www.thebatavian.com/press-release/gcedc-board-accepts-applications-for-incentives-for-warehouse-dri-project-and-two#comments https://www.thebatavian.com/press-release/gcedc-board-accepts-applications-for-incentives-for-warehouse-dri-project-and-two Jul 2, 2021, 11:52am Gallina Development GCEDC Board accepts applications for incentives for warehouse, DRI project, and two solar projects Press Release <p><em>Press release:</em></p> <p>The Genesee County Economic Development Center (GCEDC) Board of Directors approved an initial application for incentives and final incentives for projects proposing to invest $18.5 million at its July 1 board meeting.</p> <p>Gateway GS LLC (Gallina Development) plans to build the third phase of its flex campus at</p>