Catco Construction https://www.thebatavian.com/ en https://www.thebatavian.com/themes/barrio_batavian/images/thebatavian_logo.png Catco Construction https://www.thebatavian.com/ Local Matters © 2008-2023 The Batavian. All Rights Reserved. Tue, 23 Apr 2024 04:58:58 -0400 https://www.thebatavian.com/themes/barrio_batavian/images/thebatavian_logo.png Mon, 01 Nov 2021 10:37:00 -0400 Supply chain issues push start of Park Road Reconstruction Project back to spring 2022 https://www.thebatavian.com/mike-pettinella/supply-chain-issues-push-start-of-park-road-reconstruction-project-back-to-spring The “new normal” has become a reality for the Park Road Reconstruction Project.

Tom Lichtenthal, assistant engineer for the Town of Batavia, this morning said the start of the $4.077 million renovation of Park Road between Route 63 (Lewiston Road) and Route 98 (Oak Street) has been pushed back until next spring due to supply chain issues caused by the COVID-19 pandemic.

“This is the result of COVID, just like we’ve seen for the last year and a half to two years in trying to get materials,” Lichtenthal said. “It’s the new normal, if you will, and it was not unexpected.”

During a pre-construction meeting last week with representatives of general contractor Catco (Concrete Applied Technologies Corp.) Construction of Alden, Lichtenthal learned that the pipe for the watermain won’t be delivered for another 12 weeks.

“That pushes the start out to mid-January, which is not a good time for this type of work,” he said. “Installation of the pipe is still the first order of business, but it’s likely delayed until the spring of 2022.”

Lichtenthal said the late start is not expected to extend the timeline for the project’s completion, which has been set for December 2022.

The scope of the work includes installation of new pavement, curbs and curbing from Lewiston Road to Richmond Avenue with sidewalks on both sides of Park Road; overlaying of pavement and installation of sidewalks on one side of the road from Richmond Avenue to Route 98, and installation of new water lines and street lights on Park Road between Route 63 and Richmond Avenue.

Previously: WROTB, Town of Batavia agree on Park Road items

Previously: Town board OKs measures to support Park Road project

]]>
https://www.thebatavian.com/mike-pettinella/supply-chain-issues-push-start-of-park-road-reconstruction-project-back-to-spring#comments https://www.thebatavian.com/mike-pettinella/supply-chain-issues-push-start-of-park-road-reconstruction-project-back-to-spring Nov 1, 2021, 10:37am Catco Construction Supply chain issues push start of Park Road Reconstruction Project back to spring 2022 mikepett <p>The “new normal” has become a reality for the Park Road Reconstruction Project.</p> <p>Tom Lichtenthal, assistant engineer for the Town of Batavia, this morning said the start of the $4.077 million renovation of Park Road between Route 63 (Lewiston Road) and Route 98 (Oak Street) has been pushed back until</p>