Skip to main content

Park Road Improvement Project

Town board OKs measures to support Park Road project

By Mike Pettinella

The Batavia Town Board on Wednesday night voted in favor of several resolutions pertaining to the Park Road Improvement Project – a $4.3 million reconstruction of the busy street that runs between Lewiston Road (Route 63) and Oak Street (Route 98).

Approvals of resolutions by the board at its monthly meeting at the Town Hall on West Main Street Road are as follows:

  • An amendment of a bond resolution of July 21 that increases the amount to be borrowed from $3 million to an estimated maximum cost of $4.3 million “to reflect the full nature of the costs of the project and to handle the higher than expected bids received.”

Town Supervisor Gregory Post said the issuance of serial bonds makes the most financial sense, especially since a large portion of the project cost will be reimbursed by the federal government and New York State.

“This gives us temporary cash flow to be able to pay the bills with the bond money and not having to take it from town accounts,” Post said. “Right now, we’re earning interest on 99.9 percent of the town’s money.”

  • A revised supplemental agreement with the state Department of Transportation that puts the total construction cost at $3,248,915 with the federal share at $2,599,132, the state share at $435,000 and the local share at $214,783, and to include a local share for the watermain and street lighting betterment at a total cost of $1,108,085.

Renovation of Park Road has been part of the town’s plan since December 2009, when it signed the original agreement with the DOT.

  • A contract in the amount of $4,077,000 with Concrete Applied Technologies Corp., doing business as CATCO, of Alden, as the lowest bidder as the general contractor for the project.

Work will consist of the installation of new pavement, curbs and curbing from Lewiston Road to Richmond Avenue with sidewalks on both sides of Park Road overlaying of pavement and installation of sidewalks on one side of the road from Richmond Avenue to Route 98, and installation of new water lines and street lights on Park Road between Route 63 and Richmond Avenue.

  • A contract in the amount of $11,200 with Ravi Engineering and Land Surveying, P.C., of Rochester, to assist the town in the design of the street lighting electrical system and review the estimate of the project.

The board tabled a resolution to amend an agreement with Western Regional Off-Track Betting Corp., raising the contribution of the parent company of Batavia Downs Gaming from $350,000 to $486,870 for enhanced aesthetics near the facility.

The resolution stipulates that WROTB make three equal yearly installments of $162,290.

Post said negotiations with WROTB are continuing.

In late August, WROTB directors approved allocating $488,000 for the enhancements due to rising costs of conduit, light fixtures and trees.

WROTB President Henry Wojtaszek said he hoped to forge a contract with the Town of Batavia for Batavia Downs to maintain trees, street lights and sidewalks, and for snowplowing of that portion of the road.

In other action, the board approved:

  • A contract for $13,250 with Ciurzynski Consulting, LLC, of Attica, for architectural and engineering sub-consultant services for improvements to the Town Hall and highway garage.

Post pointed out several issues with the Town Hall, including heating/air conditioning problems and flooring and the need to reconfigure work space, and with the highway garage, including replacement of the roof and insulation to facilitate cold storage to warmer storage.

  • A contract for $9,500 with Wendel Companies of Rochester to assist in updating the town’s solar law.

Currently, the town is enforcing a moratorium on solar projects while a committee works to formulate a comprehensive solar ordinance. Chaired by Town Council member Chad Zambito, the committee is scheduled to meet again on Sept. 23.

Authentically Local