Skip to main content

Route 98 resurfacing project begins Monday in Batavia

By Billie Owens

A $500,000 project to resurface state Route 98 (Oak Street) in the City of Batavia gets under way Monday, according to the New York Department of Transportation.
 
Keeler Construction of Albion, Orleans County, was awarded the construction contract. The project is funded through the federal American Recovery and Reinvestment Act of 2009 (ARRA).
 
“This resurfacing work is one of many DOT projects that will improve our transportation system and bring jobs to communities across the state,” Acting DOT Commissioner Stanley Gee said in a press release. “I thank Governor David Paterson for certifying this important infrastructure project and our congressional delegation for bringing critical economic-recovery funding to New York State.”
 
Of the $1.1 billion New York State received for highway and bridge projects under ARRA, a total investment of $74 million in economic-recovery funding is expected to be certified for Rochester-area communities.
 
The Route 98 (Oak Street) project stretches from Main Street to Noonan Drive, just south of theThruway. It's preventative maintenance, amied at providing a smooth riding surface and extend the life of the pavement. The work includes pavement joint repairs, pavement milling and overlay; drainage structure repairs; an upgraded traffic signal at the intersection of Rt. 98 and Richmond Avenue; installation of detectable warning surfaces at sidewalk ramps; and fresh pavement markings. 
 
The current four-lane road will be re-painted to provide one 14-foot travel lane in each direction and an eight-foot parking lane along both sides. Left turning lanes will be included at the intersection of Richmond Avenue.
 
A single lane of northbound and southbound traffic will be maintained throughout the construction phase. Street parking will be permitted along Route 98, except during a two-week period (approximately) from mid-July through the end of July. That's when milling and paving operations are scheduled to take place. Access to all driveways and side streets will be provided at all times.
 
Initial work includes spot pavement repairs and adjustment of manholes and drainage structures in the northbound curb lane. The project is expected to be finished before school starts in September, possibly sooner.

“The State Department of Transportation office serving the greater Rochester region has been able to double its preventative maintenance paving program this year because of the economic recovery funds provided to us,” Acting Regional Director Robert Traver said. “A strong preventative maintenance program is critical in keeping the state’s transportation system in a state of good repair for the thousands of citizens who use it.”
 
Traver noted the significant support of the congressional delegation, Senator Michael Ranzenhofer and Assembly member Steven Hawley in delivering this regional transportation project.
 
The economic-recovery funds coming to New York State for transportation projects must follow the same process required for distributing all federal transportation funds. The funds are allocated to projects that are selected by the 13 regional Metropolitan Planning Organizations (MPOs) across the state, which are comprised of local elected officials, local transit operators and NYSDOT representatives. MPOs vote unanimously on projects for their Transportation Improvement Program, and the projects are candidates for economic-recovery funds. The preventative maintenance project was approved by the Genesee Transportation Council to be eligible to receive ARRA funding.
 
Similarly, regions of New York State without MPOs are served by NYSDOT, which consults with local elected officials and selects projects for the Statewide Transportation Improvement Program. The department worked with local officials and the governor’s Economic Recovery Cabinet to identify shovel-ready projects eligible for recovery funds.

Authentically Local