Skip to main content

City DPW chief anticipates resumption of City Centre mall replacement project

By Mike Pettinella

City of Batavia Public Works Director Matt Worth is hopeful that the City Centre roof alternations and replacement project will resume sooner rather than later.

“We’re just waiting for a little bit of clearance (from New York State regarding work guidelines) and a little bit of good weather for that to move forward,” Worth said, talking about a $664,080 contract the City forged with Grove Roofing Services Inc. of Buffalo.

Close to a year ago, City Council selected Grove Roofing to replace several sections of concourse roof and the skylights, a project that will encompass about 80 percent of the roof, Worth said.

The roofers had delivered some materials and we’re just about to start the tear-off when the COVID-19 shutdown came.

“They tried to do some things that they could do safely – like putting up safety barriers and things like that, but held off getting into the project, in accordance with the (state) directives,” Worth said.

The project entails removing the existing insulation and roof material, installing new insulation and a new rubber membrane roof.

Worth said about 5 percent of the job will deal with replacing the metal roof deck beneath the roof “that we know is deteriorated – an area down by Sunny’s (Restaurant) and a wing down off of City Hall by Dr. Yaeger’s (office).”

The project is being paid for by funds taken from the City’s Facility Reserve.

In mid-April, Council voted to take $30,000 from the Facility Reserve (which was at $238,000) to cover unexpected construction costs.

A recent design change with the skylight roof covering resulted in an additional expense of $13,040. The remaining nearly $17,000 will be available in case of a condition change that needs to be addressed right away once the main roof construction work starts, Worth said.

Authentically Local