Skip to main content

City Council set to receive update on Jackson Square project consultant selection process

By Mike Pettinella

The City of Batavia is moving forward with the design and construction of the $750,000 Downtown Revitalization Project at Jackson Square, the popular music venue tucked in between Jackson and Center streets.

Public Works Director Matt Worth on Friday said his office has received 11 proposals from professional firms seeking to take the lead for the project that calls for the following upgrades: decorative pavement, enhanced lighting, relocation of electrical utilities, planters, benches, tables, chairs for seating and a new stage.

The cost of this work, $750,000, is the full amount of the grant issued as part of the state’s DRI program, and the expense of the design firm will be charged against the DRI grant as a project cost.

A draft resolution to enter into an agreement with an engineering or architectural firm is on Monday night’s City Council Conference Meeting agenda. The meeting is scheduled for 7 o’clock at the City Centre Council Board Room.

A letter from Worth dated Sept. 25 went out to consultants, inviting them to “provide a proposal of project understanding and qualifications” for engineering and design services. The letter indicated the city “strongly encourages participation of MWBE (Minority and/or Women-owned Business Enterprise) and SDVOB (Service-Disabled Veteran-Owned Small Business) firms.”

The state is stipulating a MWBE participation of 30 percent and an SDVOB goal of 6 percent.

Worth said a team is scoring the proposals and will announce its selection in several weeks.

“Because this project is a little different – not a straightforward, engineering street design (for example), this could end up being a team approach,” he said, advising that the consultant could be an engineering firm, design professional, landscape architectural company, or a combination.

As far as the timetable is concerned, Worth’s letter indicates investigation and design work to be performed next spring and progress through to construction in the fall – after the Jackson Square performance season. It also states that two public information meetings will be scheduled.

On another front, Worth said work on the City Centre Mall roof is complete.

“The warranty is in place, so we’re moving to the next phase,” he said. “The Mall Feasibility Study is wrapping up right now and we’ll be jumping into the DRI project with the mall concourse, which will probably include some additional roofing as well.”

Worth said specific plans for the mall project will be based on the feasibility report recommendations.

Other topics on Monday’s agenda include:

-- A public hearing to amend the Batavia Municipal Code to include public garages (auto repair stations) in I-1 (Industrial) zones with a special use permit. This action stems from a request by Batavia businessman Eric Biscaro, owner of Classic Home Improvements, to place an auto repair shop on his property on Ellicott Street.

-- A resolution accepting public dedication of Carolwood Drive Extension, also known as Clinton Gardens Subdivision Part 21A, as a result of Batavia Homes and Development’s completion (and municipal approvals) of the installation of storm water system, sanitary sewer system, water main, house services and street paving to add five more building lots on the street.

-- A resolution to accept a $6,000 grant from The Batavia Rotary Club and Rotary Foundation to the City of Batavia Youth Bureau to support outdoor recreation through the purchase of kayaks, kayak launch, paddles and vests. The youth bureau has indicated that it will teach kayaking as part of its youth center and summer recreation programming, and also will incorporate STEM (Science, Technology, Engineering, Math) education through this activity.

Authentically Local